Green Star FAQs
Green Star - Design & As Built v1.2
Innovation / D - Innovation Challenge: High Performance Site OfficeF-00278 - What is the process for upgrading my project from Design & As Built to Green Star Buildings?
***** Updated 17/02/2026 *****
Updated on 17/02/2026 to reflect the process for upgrading to Green Star Buildings v1.1 and the cut off date for Green Star Buildings v1.
The Upgrade Process:
1) Reach out to the GBCA meteam@gbca.org.au and let us know that you are interested in upgrading to Green Star Buildings. The Market Engagement...
Published on Wed, 25 Feb 2026
F-00488 - Can projects pro-rata the number of showers required?
Yes, a pro-rata approach to calculating the number of showers required for the number of regular building occupants can be taken per the tables below:
Table 1 – Pro-rata approach for Green Star – Design & As Built and Green Star – Interiors projects
Occupants
Showers
0 - 12
1 Unisex
13 - 49
2
50 - 99
3
100...
Published on Mon, 26 May 2025
F-00095 - Can I use 'For Construction' drawings in the As Built submission?
Yes. The GBCA requires evidence that the drawings supplied are as constructed, whether they have an ‘As Built’ stamp or not. 'For Construction' drawings are acceptable provided they are accompanied by formal confirmation from the head contractor or other relevant professional(s) that the For Construction drawings depict the site as-built...
Published on Tue, 31 Mar 2020
F-00083 - Does there need to be 500cm2 of soil surface area per every 10m2 section of nominated area?
No. Whilst the intention is to have plants evenly distributed throughout the floorplate of a building, it is not a requirement that there be 500cm2 of soil surface area in every 10m2 of nominated area.
Compliance can be demonstrated by showing that the total percentage of soil surface area within each...
Published on Mon, 11 Nov 2024
F-00397 - Do I need to test all apartments for airtightness in Green Star?
No, all apartments are not required to be tested for air-tightness in Green Star.
Project teams may test a minimum of 10 dwelling units or 10% of the total number of dwelling units, whichever is greater as sample units to satisfy the Testing Area Requirements.
The sample units selected must include:
A representative...
Published on Wed, 17 Jul 2024
F-00367 - When should project teams submit for the optional Designed Assessment / Design Review?
The GBCA has no specific requirement as to when registered projects should submit for a Designed Assessment. Below is some guidance to help establish the best timing for your project. This supplements information provided in the rating tool Submission Guidelines.
Purpose
A Designed Assessment (or Design Review under the Legacy rating tools)...
Published on Wed, 24 Jan 2024
F-00335 - How can project teams demonstrate compliance when a contractor has become insolvent?
The GBCA recommends that, when a contractor, sub-contractor, consultant, or other party involved in a Green Star registered project is unable to complete project works or provide documentation for the Green Star submission due to insolvency or another unforeseen event, the project team should contact the GBCA as soon as...
Published on Tue, 1 Aug 2023
F-00286 - Instances where a technical question no longer needs to be submitted by a project team
Technical questions related to Innovation were previously marked as free of charge. However moving forward Innovation related technical questions will be charged the standard fees of $220 (excl. of GST) as per a technical question. The following is a list of all places in the rating tool where a technical...
Published on Mon, 17 Oct 2022
F-00289 - Can products/materials be weighted against the total material cost for the Circular Economy Leadership Challenge?
Yes, in the Circular Economy Leadership Challenge, project teams may weight the chosen products against the total material cost associated with the project in lieu of the total project cost.
This is on the basis that the Leadership Challenge focuses on the circularity of materials/products within a project therefore the alternate...
Published on Mon, 19 Sep 2022
F-00240 - Does the GBCA accept carbon offsets?
Yes, where credits in Green Star allow the use of carbon offsets the GBCA will accept electricity and nature based offset initiatives that have been certified by the standards and labels listed within the Carbon Positive Buildings and our Net Zero Ambitions document. For note, this list is not exhaustive...
Published on Tue, 13 Sep 2022
F-00174 - How do I calculate C&D Waste points when delivering an integrated Interiors project within a Design & As Built building?
Fixed Benchmark Pathway (22A)
Projects teams delivering a Green Star rated Interiors project within a Green Star Design & As Built rated base building may aggregate the base building and fitout construction and demolition waste to determine the maximum waste allowance based on the combined GFA and NLA.
Up to one (1)...
Published on Mon, 10 Jul 2023
F-00295 - Can projects claim an innovation point for rectifying air leaks identified during air permeability testing?
Yes.
Projects may target one (1) point through 30B Market Transformation under Green Star - Design & As Built by conducting additional leakage diagnostics to document leaks found during testing, rectifying and reporting at least one major defect identified during air permeability testing to all stakeholders, in addition to targeting and...
Published on Fri, 21 Oct 2022
F-00233 - For the 'High Performance Site Offices' Innovation Challenge, can I use alternative insulation values for site sheds?
For the purposes of the 'High Performance Site Offices' Innovation Challenge, project teams can target the thermal comfort credit criteria within the checklist by implementing R3.8 insulation in the roof and R2.8 in the walls of temporary site facilities.
Please include a copy of this response in your submission.
Published on Fri, 17 Sep 2021
F-00175 - Can I use theoretical calculations to demonstrate compliance with the Ultra-Low VOCs innovation?
Yes. Projects targeting the Exceeding Green Star Benchmarks for Indoor Pollutant innovation UItra-Low VOC Paints may use theoretical calculations to determine the grams of VOC per litre (g/L) in addition to the current methods of demonstrating that a paint, adhesive or sealant complies with this criterion. Total VOC (TVOC) values...
Published on Wed, 5 May 2021
F-00191 - Can projects target 'Designing for Robustness' credit from 'BREEAM' as innovation under Global Sustainability?
Yes.
Projects pursuing certification under Green Star - Design & As Built, and Green Star - Railway Stations may target the 'Designing for Robustness' credit from the 2015 'BREEAM In-Use International' Technical Manual.
One (1) point is available where all compliance requirements for the credit has been addressed and evidenced as per...
Published on Mon, 12 Apr 2021
F-00181 - How do I know what type of documentation is accepted for a Design Review rating?
We’ve developed a short guidance document for project teams on what level of documentation is acceptable for Design Review – Green Star Design & As Built and Green Star – Interiors.
This Design Review Guidance provides answers to common questions asked by project teams. The Guidance - Submitting for Design Review document is...
Published on Fri, 13 Nov 2020
F-00171 - When is an Independently verified performance certification required when targeting Stormwater Pollution Targets ?
For the purposes of credit criteria - Stormwater Pollution Targets, project teams are only required to use independently verified performance certification for the equipment, where a treatment train that does not contain biological treatment is being used to achieve the Pollution Reduction Targets in column C of Pollution Reduction Targets...
Published on Fri, 4 Sep 2020
F-00122 - Can I promote my project if it is registered for Green Star, but not yet certified?
Before achieving certification you can promote your Green Star registered project in writing, but cannot use the Green Star logo or Green Star certification trade mark.
The Green Star certification trade mark can only be used once the project is certified. The Marketing and Style Guide explains how Green Star certified projects can...
Published on Mon, 6 Jan 2020
F-00036 - 19A - Life Cycle Assessment in Green Star - Design & As Built v1.2
In Regards to 19A - Life Cycle Assessment in Green Star - Design & As Built v1.2 the GBCA clarifies the following:
19A.1 – Comparative Life Cycle Assessment - Are exceeding benchmark points available for operational energy improvements beyond the three (3) capped points
The GBCA clarifies that exceeding benchmark points can...
Published on Tue, 29 Jan 2019
F-00006 - Is the supporting documentation listed in each credit required for submission?
No. All supported documentation listed for each credit in the Submission Guidelines are suggestions only, unless specified otherwise. Alternate documentation to those listed can be used by project teams to demonstrate credit compliance if it adequately supports the claims made within the Submission Templates.
Published on Tue, 26 Jun 2018
Disclaimer
When used on Green Star projects, make sure to:
These FAQs are:
- provided as additional technical assistance for Green Star users.
- optional and free to use on Green Star projects.
When used on Green Star projects, make sure to:
- state the FAQ number on the Submission Template.
- click on "Download" to save the FAQ.
- include the PDF in the submission.
The GBCA reserves the right to add or remove FAQ at our discretion.