Error. File Path Not Found:
C:\inetpub\wwwroot\gbca.org.au\trunk\greenstar-projects\images\projects
-
Status Certified
-
Address
Level 24 and 25 360 Elizabeth Street Melbourne VIC
- Certified Tue 8 Sep 2015
- Score 60
- Applicant(s)
ME Bank
-
Project Manager
Colliers
-
Architect
Colliers
-
Building Services Engineer
Simpson Kotzman Pty Ltd
-
Local Planning Authority
City of Melbourne
-
Main Contractor
FDC Construction & Fitout Pty Ltd
-
ESD Consultant
Individuals in Transit
-
Acoustic Consultant
Acoustic Consulting Australia
|
Category Achievements
Management
- A Green Star Accredited Professional is a principle participant in the project team to provide advice on the Green Star aims and processes from design through to the delivery.
- Comprehensive pre-commissioning, commissioning and quality monitoring occurred for the tenancy.
- Provided a comprehensive, yet simple Tenant Guide for the relevant building and tenancy systems to the users and owner.
- The contractor implemented a Waste Management Plan and 80% of construction waste by weight was re-used or recycled during fitout works.
Indoor Environment Quality
- Internal noise levels are minimised to improve occupant comfort from building services and outside entities.
- All installed carpets are low in volatile organic compounds.
- All accessible supply air ductwork has been cleaned prior to occupancy.
- Plants with positive indoor environment benefits are distributed across the fitout at one large (or two small) pots per workstation, in line with a Horticultural Maintenance Plan.
- Flat-screen, mounted workstation monitors are provided with the fitout and can be manually adjusted to provide the ability to avoid daylight glare.
- Installed high frequency ballasts reduce occupants' eye strain from low frequency flicker.
- 60% of workstations have direct line of site to outdoor environments.
- All asbestos found during construction works has been removed.
Energy
- The tenancy achieves at least a 5 Star NABERS (formerly ABGR) rating, with an additional 40% CO2 reduction.
- Sub-metering is installed for tenancy lighting and small power consumption.
- Individual switches are installed for enclosed spaces and zones in accessible locations.
Transport
- Many public transport networks operate in close proximity with frequent peak hour services.
- Cyclist facilities are available, with secure bicycle storage for 10% of tenancy occupants and accessible shower and change facilities.
Water
- The use of potable water is greater than a 'best practice' scenario.
- All dishwashers in the tenancy are 5A rated.
Materials
- The tenancy provided workstations with reduced environmental impact, relative to available alternatives.
- Flooring throughout the tenancy has a reduced environmental impact, relative to available alternatives.
- Walls and partitions in the tenancy have a reduced environmental impact, relative to available alternatives.
- The tenancy provided chairs with reduced environmental impact, relative to available alternatives.
- The tenancy provided storage units with reduced environmental impact, relative to available alternatives.
Land Use & Ecology
- The building management is contractually required to implement environmental initiatives concerning maintenance and monitoring of various tenancy aspects.
- The tenancy lease agreement requires participation in a number of monitoring and maintenance intiatives for the tenancy.
- 75% of the tenancy fitout space was preciously tenanted.
Emissions
- All refrigerants used have an Ozone Depleting Potential (ODP) of zero.
- All thermal insulation avoids the use of ozone-depleting substances in both manufacture and composition.